Loading

Faraj Allah

A- Warehouses, refrigerators and garage project(Muharram Bek area)

Flat metal truss 12000 m2 Bottom truss 3 buildings.

First: the refrigerator building

Concrete building of 3 floors (refrigerators and 2 floors of an administrative building) with a surface of 2200 meters.

Second: the garage

The garage is a metal truss with a flat 4000 meters.

Third: the warehouse building
Fourth: Service area
  • 01 Transformer building.
  • 02 Generator building.
  • 03 TBoiler area.
B- Cake and Biscuits Factory Project(New Borg El Arab area).

Concrete structure with a flat surface of 7200 meters (consisting of 3 floors).

Almonairy (wet corn mill) specializes in producing glucose, fructose, corn starch, corn oil, gluten feed which uses in variety industries such as paper, food production, pharmaceutical productions, etc...

An administrative building with a flat area of 800 meters(consisting of 4 floors).

The project was implemented from excavation works to internal and external finishes, installation works and project delivery.


C- Concentrates Factory Construction Project(New Burj Al Arab Area)
  • 01 It is a metal truss with a flat surface of 5400 meters in addition to an administrative building of basement, ground and 3 floors.
  • 02 The construction was carried out from excavation and backfilling to civil works, finishes and mechanical works.
  • 03 Factory internal road works.
  • 04 In addition to the service area with a flat area of 2000 square meters,the area contains:

    1. 1-Sewage treatment plant.
    2. 2-Treated water tank.
    3. 3-Cooling towers.
    4. 4-Boiler area.
    5. 5-Building of generators and transformers.
D- Construction of warehouse building project (New Burj Al Arab area)
  • 01 Concrete structure with a flat surface of 4800 meters from basement, ground and first floor.
  • 02 The last floor covering a metal roof.
  • 03 The construction was carried out from excavation and backfilling to civil works, finishes and mechanical works.
  • 04 Factory internal road works.